BRIDGE INVESTMENT OFFERING · CONFIDENTIAL · ACCREDITED INVESTORS ONLY

PROJECT
IRIS

Griffin, Georgia·261 Acres·1.5 GW Georgia Power Substation

A utility-delivered AI infrastructure campus positioned alongside a Georgia Power transmission-fed substation planned directly on-site — sized at full capacity from energization. Not competing for power. The power is being built here.

$2MBridge Raise
2x–8xTarget Return
12 Mo–5 Yr+Exit Window
1.5 GWUtility Capacity
Request Materials Learn More
1.5 GW On-Site Substation 261 Acres · Griffin, Georgia $2M Bridge Offering 2x Return · 12–18 Months 4x Return · 2–4 Years 8x Return · 5 Years+ 1st Lien Security FIFO · No Equity Dilution Georgia Power Partnership 765 kV Backbone Fed Diamond Infrastructure Group 1.5 GW On-Site Substation 261 Acres · Griffin, Georgia $2M Bridge Offering 2x Return · 12–18 Months 4x Return · 2–4 Years 8x Return · 5 Years+ 1st Lien Security FIFO · No Equity Dilution Georgia Power Partnership 765 kV Backbone Fed Diamond Infrastructure Group

Power Delivered,
Not Promised

Most AI infrastructure sites begin with a hope for power. Developers spend years — and tens of millions of dollars — trying to confirm utility capacity that may never materialize. Queue positions are lost. Timelines slip. Capital erodes.

01

Utility Coming to the Land

Georgia Power is constructing a new transmission-fed regional substation directly on the Project IRIS property. DIG is not competing for a queue position. The utility is building its infrastructure on DIG's land.

02

765 kV Backbone — Full Capacity from Day One

The substation is fed from Georgia Power's 765 kV backbone and sized at 1.5 GW at full capacity from energization. No ramp-up constraints. No phased utility buildout that doesn't happen.

03

Coordinated Development Advantage

Grading, easements, transmission routing, and long-lead equipment procurement can be sequenced alongside Georgia Power's construction timeline — dramatically compressing Phase 1 delivery versus greenfield origination.

1.5 GW

Georgia Power transmission-fed substation planned directly on the 261-acre Project IRIS site in Griffin, Georgia. Fed from the 765 kV backbone. Sized at full capacity from energization.


~45 Miles South of Atlanta · Spalding County, Georgia

12–18 Mo

Estimated Phase 1 energization timeline, coordinated alongside Georgia Power's substation construction schedule. Significantly faster than the 3–7 year greenfield utility origination path.

Bridge Offering Structure

Offering Size$2,000,000
Min Investment$200,000
Target Return2x – 8x
Return Window12 Months – 5 Years+
Security1st Lien — Georgia Power Substation Easement & Site Control
PriorityFIFO — First-in, First-out
Repayment TriggerInstitutional Close or Qualifying Presale Event
Investor TypeAccredited Investors Only

Bridge investors are repaid from first proceeds before any fees, distributions, or equity allocations. No competing claims on this disbursement. No construction or operations exposure.

Near-Term Exit

$200K in → $400K out

Institutional presale of utility easement position at initial close. First-out repayment before any other distribution.

2x 12–18 Months

Mid-Term Exit

$200K in → $800K out

Phase 1 hyperscale anchor lease executed. Land + power platform sold to infrastructure fund at utility interconnection.

4x 2–4 Years

Long-Term Exit

$200K in → $1.6M out

Full 1.5 GW campus platform sale at institutional pricing. Multiple phases energized, anchor tenants in place.

8x 5 Years+

Return scenarios are projections based on comparable platform transactions. Not a guarantee of future performance.

261 Acres + 1.5 GW Utility Infrastructure

Griffin, Georgia is 45 miles south of Atlanta — fiber-rich corridor, established labor market, I-75/I-85 proximity, water access. A location institutional data center operators actively target.

1.5 GW Georgia Power Substation On-Site

Transmission-fed regional substation planned directly on the Project IRIS parcel. Fed from the 765 kV backbone. No queue. No wait. Sized at full capacity from energization.

📐

261 Acres · Controlled Site

Single contiguous assemblage in Spalding County, Griffin GA. No adjacent land assembly risk. No competing parcels. Master-planned for phased data center campus development.

🔌

Phase 1 · 12–18 Month Timeline

Coordinated development alongside Georgia Power's construction schedule enables accelerated Phase 1 energization — significantly faster than greenfield utility origination.

🛣

Griffin, Georgia · Infrastructure Hub

~45 miles south of Atlanta. I-75/I-85 proximity, fiber-rich corridor, established labor market, water access. Institutional-quality location for hyperscale and AI compute.

🏢

Campus Master Plan · ~1.5 GW IT Capacity

Phased expansion toward 1.5 GW of IT load capacity. Each phase independently capitalized. AI, hyperscale cloud, advanced manufacturing, and mission-critical applications.

🌐

Utility Collaboration Already Underway

Grading, easements, transmission routing, and long-lead equipment procurement coordinated alongside Georgia Power's construction. DIG embedded in the utility's planning.

How & When Investors Are Repaid

Three independent exit paths — each with defined conditions. Bridge investors are positioned in front of all of them.

01

Institutional Presale or Presale Event

12–18 Months 2x Return

Qualifying presale of utility easement position based on confirmed Georgia Power substation commitment and site control. Bridge investors repaid in full from first proceeds before any other distribution.

02

Platform Sale at Utility Interconnection

2–4 Years 4x Return

Execution of the formal utility interconnection agreement with Georgia Power triggers institutional platform sale. Land + power + interconnection rights packaged and sold to an infrastructure fund.

03

Full Campus Platform Realization

5 Years+ 8x Return

Sale of the fully assembled Project IRIS campus — land, utility easements, interconnection rights, anchor tenant agreements, and master plan entitlements — at full 1.5 GW campus valuation.

How This Structure Protects Investors

Risk Category How It Typically Hurts Investors How Project IRIS Addresses It
Power Availability Most sites have no confirmed power. Years of development may pass before utility capacity is confirmed — if ever. Georgia Power's substation is planned on-site. Utility infrastructure is coming to the land. Power availability risk structurally removed before bridge capital is deployed.
Execution Timeline Projects with undefined paths to exit expose investors to compounding uncertainty and capital lock-up. Three independent exit paths with defined conditions: 2x at 12–18 months, 4x at 2–4 years, 8x at 5+ years. Capital is not trapped in an undefined timeline.
Construction Exposure Early investors often sit behind construction debt, cost overruns, and tenant risk with no priority protection. Bridge investors are repaid at the offload event — structurally upstream of construction, operations, and tenant risk. Zero buildout exposure.
Collateral Value Early-stage equity is typically unsecured. No hard asset backing the return obligation. 1st lien security on site control and Georgia Power substation easement. Hard-asset collateral backing the return obligation at every exit path.
Dilution & Subordination Later capital raises can dilute early investors or subordinate their position in the capital stack. Bridge investors are not equity holders. Return is a senior contractual obligation. FIFO structure. No equity dilution. No subordination.

The Firm Behind Project IRIS

Diamond Infrastructure Group was established to identify, assemble, and develop strategic infrastructure platforms capable of meeting the unprecedented power demand of the AI era. Our focus extends beyond acquiring land — we develop utility-integrated campuses that combine transmission access, energy infrastructure, and institutional-grade planning into investment platforms designed for long-term value creation.

Project IRIS is DIG's second full flagship development.

  • Power-first site origination strategy — utility confirmation precedes capital deployment
  • Utility-integrated campus development model — not land speculation
  • Institutional-grade execution across site control, engineering, and capital formation
  • Deep utility relationship management — embedded in Georgia Power's planning process
  • Pre-development expertise built from nuclear power engineering, generation-side utility operations, and PPA structuring across major utilities

"Power has become the defining constraint of the AI era. Diamond Infrastructure Group was established to identify, assemble, and develop strategic infrastructure platforms capable of meeting this unprecedented demand."

— Diamond Infrastructure Group, Project IRIS Investment Memorandum

Project IRIS — Second DIG Flagship

Located in Griffin, Georgia — 45 miles south of Atlanta — Project IRIS has evolved into a 261-acre master-planned AI infrastructure campus positioned to capitalize on Georgia Power's confirmed utility expansion directly on-site.

Ready to Participate?

This offering is open to accredited investors. Minimum investment $200,000. Subscription documents and additional materials available upon request.

Request Subscription Documents General Inquiry